Planning, delivery and supervision of nuclear projects — including decommissioning and dismantling. With the licences that must be in place for it.

Approval

Licence
§ 25 StrlSchG
Testing
§ 12b AtG
Sabotage protection
ja
Release
§ 58 StrlSchV
What we take on

In nuclear facilities it is the proof that decides, not the quote

Anyone who wants to work in a controlled area needs more than expertise: a licence, a passed reliability check and complete documentation.

COPLA Burg GmbH has worked in nuclear engineering for decades and holds the licence under § 25 of the Radiation Protection Act for work in other operators' radiation protection areas. On top of that come the reliability check under § 12b of the Atomic Energy Act and the sabotage protection measures. Without those three building blocks nobody enters a controlled area — however well they can weld.

Power generation in Germany has ended; the work has not. Decommissioning and dismantling tie up staff for years — people who are equally at home with radiation protection, cutting technology and documentation. That is where our focus lies today. Our people have worked at the Grohnde, Lingen and Nord nuclear power plants, among others.

Dismantling and operation

  • Dismantling fitters and demolition specialists
  • Radiation protection workers and operational radiation protection specialists
  • Decontamination specialists
  • System labelling and plant documentation
  • Cutting and packaging technology, waste treatment

Planning and supervision

  • Project engineers for nuclear power plant dismantling
  • Systems engineers for electrical and I&C engineering
  • Physicist for dismantling and repository documentation
  • Supervision under the KTA rules
  • Clearance measurement and documentation under § 58 StrlSchV
Careers in the nuclear division

Currently open with us

15 positions are currently open in the nuclear division — permanent contracts, pay at the end of the month and training we pay for.

All 15 positions in Nuclear To the careers area

On film

Nuclear engineering, explained in two minutes

The film shows how a nuclear assignment runs — from the access check through transport to interim storage.

The video only starts when you click. Until then, no data is sent to third parties.

In brief

What counts in nuclear engineering

  1. 01

    Licence under § 25 StrlSchG and reliability check under § 12b AtG.

  2. 02

    Planning, supervision, decommissioning and dismantling — supervised and documented.

  3. 03

    Cleared means released: first the proof, then the part.

Dismantling

From component to released package

  1. 01Enclosure

    A tented enclosure under negative pressure, so nothing escapes.

  2. 02Cutting

    The vessel is cut into segments, remotely or by hand.

  3. 03Packaging

    Declare the package, document it, release it.

Insights

Where the proof comes before the work

In nuclear facilities it is not the quote that decides but the licence: access, expertise, measurement, documentation.

Cooling tower of a nuclear power plant in the evening light
Plants in operation and in dismantlingWhether it is a turnaround or decommissioning — access hangs on the same check under § 12b of the Atomic Energy Act.
Two people in protective suits at a measuring station, warning sign in the background
Working in the controlled areaProtective suit, dosimeter, instruction: anyone going in has provided the proof beforehand.
Pressure gauge on a stainless steel pipeline
Measure, check, recordEvery value is recorded. Without a record there is no release — neither for a component nor for a package.
Three focal points

What nuclear assignments hang on

Before the work comes the licence, after the work the proof. In between lies what the specialist was brought in for.

01

Access

Reliability check, expertise, instruction, dosimetry — only then does the airlock open.

02

Dismantling

Dismantling, cutting, decontamination — planned by trade, documented by component.

03

Clearance measurement

Measure, assess, record. Without release, no package leaves the controlled area.

Explained

What § 25 StrlSchG means in practice

The section sounds like a formality. In fact it decides whether a contractor may send its people into your plant at all.

Licence under § 25 of the Radiation Protection Act

A contractor deploying staff in someone else's radiation protection areas needs an official licence to do so. It is not granted across the board: it requires expertise in radiation protection, a suitable organisation and the reliability of those responsible. COPLA Burg GmbH holds this licence — the entry ticket without which no quote is worth anything.

Reliability check under § 12b AtG

Every person who is to be granted access to a nuclear facility is checked for reliability by the competent authority. The procedure needs lead time and cannot be speeded up. That is why, with every nuclear enquiry, we ask first for the start date and plan backwards — not the other way round.

Release under § 58 StrlSchV

Material leaving a nuclear facility has to be clearance-measured and documented. During dismantling this evidence is not an appendix but a work package in its own right — and one of the reasons we also have physicists and documentation specialists on our books.

Further reading: What contractors specifically have to prepare is set out in our guide § 25 StrlSchG: what the licence means for contractorsThe full list of approvals can be found under Certificates & approvals.

How it works

Five steps to access

The route into a controlled area is longer than into a chemical plant. But it can be planned — if you start early enough.

  1. 01Clarify the requirement

    Plant, activity, area, dose relevance and time window. From that follows which proof is needed.

  2. 02Select the staff

    We propose specialists with matching experience and radiation protection expertise already in place.

  3. 03Start the reliability check

    The check under § 12b AtG is set in motion. Its duration determines the earliest possible start date.

  4. 04Instruct and examine

    Radiation protection instruction, occupational health checks, plant-specific training, dosimetry.

  5. 05Assignment and documentation

    Work under your supervision; dose records, activity records and release documents run alongside.

What it costs

What the price depends on in nuclear work

On top of the usual factors, three particulars apply here:

Factor 01

Approval effort

Reliability checks, expertise and plant-specific training are up-front work that falls due before day one.

Factor 02

Dose relevance

Work in the controlled area needs more equipment, more monitoring and shorter time on site per person.

Factor 03

Documentation

Evidence and clearance measurement are work packages in their own right, not an add-on.

Important for your planning: The limiting factor is almost never the price but the lead time of the official check. Ask earlier than you are used to from other trades.

Nuclear power plant site from the air
Lead time

Access is the long part, not the work

In nuclear work, weeks lie between the go-ahead and the first working day: reliability check, radiation protection expertise, occupational health checks, instruction on site.

Planning that lead time only once the need is there means losing it twice over. Our people bring the proof with them — and we keep it valid.

  • Reliability check under § 12b AtG already in place
  • Radiation protection expertise, kept up and refreshed
  • Licence under § 25 StrlSchG for our own deployment
FAQ

Nuclear engineering — what clients ask

May your staff work in controlled areas?

Yes. The basis is our licence under § 25 of the Radiation Protection Act for work in other operators' radiation protection areas, together with reliability checks and sabotage protection measures. Without that licence the assignment would be legally impossible, whatever the person's qualifications.

How long does the reliability check take?

The duration is set by the competent authority, not by us. Allow several weeks and report your needs correspondingly early. Where possible we propose specialists whose check is already in place and still valid.

Do you also do decommissioning and dismantling?

Yes, that is our main focus in nuclear work today. We supply staff for demolition, decontamination, cutting and packaging as well as for dismantling engineering, system labelling and repository documentation.

Who is responsible for radiation protection?

Responsibility for radiation protection at the plant stays with the operator. We provide the expertise and the required proof on the contractor's side and work under the supervision of your radiation protection officer.

Which rules do your people work to?

Depending on the task, the KTA rules, the Atomic Energy Act and the Radiation Protection Ordinance — for example § 58 StrlSchV for releasing material from radiation protection areas. Which rules apply in detail is set by your plant.

Do you also work on power plants outside the nuclear field?

Yes. Power plant construction and energy technology are a reference area in their own right — from the new-build plants at Lippendorf, Boxberg and Jänschwalde through BoA Neurath to the Walsum combined heat and power plant. More on that under Industrial Services.

Next step

A dismantling project or staff needed in the controlled area?

Tell us the plant, the task and the date you want. We work the lead times back and tell you honestly whether the date will hold.

Send an enquiry 0203 73 99 799-0

Dismantling work in an industrial plant